Sizing Compute and Storage Resources for
Workload Management

Compute and storage requirements for each component are key considerations when you size the solution.
Virtual Machine
Nodes
Total vCPUs
Total Memory
Total Storage
Supervisor Cluster control plane
(small nodes - up to 2000 pods per Supervisor cluster)
3
12
48 GB
200 GB
Registry Service
N/A
7
7 GB
200 GB
Tanzu Kubernetes Cluster control plane (small nodes)
3 (per cluster)
6
12 GB
48 GB
Tanzu Kubernetes Cluster worker nodes (small nodes)
3 (per cluster)
6
12 GB
48 GB
NSX Edge node
2
16
64 GB
400 GB