Patching the Management and Workload Domains
Once
SDDC Manager
is upgraded to 5.2 or later, a
new option for patching VMware Cloud Foundation
components is available in the SDDC Manager UI
. - Download the async patch bundles. See Downloading VMware Cloud Foundation Upgrade Bundles.
- SDDC Managermust be version 5.2 or later. See Apply the VMware Cloud Foundation 5.2.x Upgrade Bundle.
The patch planner
provides the ability to apply async patches to workload domain components. If you
are connected to the online depot, async patches are available in the patch planner.
If you do not have access to the online depot, use the Bundle Transfer Utility to
download async patches and add them to an offline depot or upload them directly to
SDDC Manager
. - In the navigation pane, click.
- On the Workload Domains page, click the domain you are patching and then click theUpdatestab.
- ClickPrecheckto run the upgrade precheck.Resolve any issues before proceeding with an upgrade.
- In the Available Updates section, clickPlan Patchingcreate a new patching plan or selectEdit Patching Planfrom theActionsmenu to modify a patching plan.You cannot plan patching if you have an existing upgrade plan. Cancel the upgrade plan to create a patching plan.
- Select the components to patch and the target versions and then clickValidate Selection.When you select a target vCenter version, the UI indicates which versions support vCenter Reduced Downtime Upgrade (RDU).
- After validation succeeds, clickConfirm.
- Review the update sequence based on your target version selections and clickDone.
- In the Available Updates screen, clickSchedule UpdateorUpdate Nowto update the first component.Continue to update the VCF BOM components until they are all updated.